=WORKDAY(start_date,days,holidays)
Related formulas
Add workdays to date custom weekends
Add days exclude certain days of week
If you need to add or subtract business days (workdays) to a date so that you can calculate a date in the future or past that skips weekends (and holidays), you can use the WORKDAY function. Holidays are optional.
In the example, the formula in D6 is:
=WORKDAY(B6,C6,B9:B11)
This adds 7 days to Tuesday, Dec 22 and returns Tuesday, January 5, 2016.
By default, the WORKDAY function will exclude weekends (Saturday and Sunday). In this case, we have also supplied a list of 3 holidays that all fall in the date range being calculated, which means both the weekends and holidays will be excluded. The following table shows which dates are excluded with and without holidays provided (shaded gray). The final dates returned by WORKDAY are highlighted in yellow
| No holidays | Holidays provided |
|---|---|
| Wed, 23-Dec-2015 | Wed, 23-Dec-2015 |
| Thu, 24-Dec-2015 | Thu, 24-Dec-2015 |
| Fri, 25-Dec-2015 | Fri, 25-Dec-2015 |
| Sat, 26-Dec-2015 | Sat, 26-Dec-2015 |
| Sun, 27-Dec-2015 | Sun, 27-Dec-2015 |
| Mon, 28-Dec-2015 | Mon, 28-Dec-2015 |
| Tue, 29-Dec-2015 | Tue, 29-Dec-2015 |
| Wed, 30-Dec-2015 | Wed, 30-Dec-2015 |
| Thu, 31-Dec-2015 | Thu, 31-Dec-2015 |
| Fri, 01-Jan-2016 | Fri, 01-Jan-2016 |
| Sat, 02-Jan-2016 | Sat, 02-Jan-2016 |
| Sun, 03-Jan-2016 | Sun, 03-Jan-2016 |
| Mon, 04-Jan-2016 | Mon, 04-Jan-2016 |
| Tue, 05-Jan-2016 | Tue, 05-Jan-2016 |
| Wed, 06-Jan-2016 | Wed, 06-Jan-2016 |
To subtract business from a date (instead of adding workdays) just use a negative value for days. For example to get a date 3 workdays before a date in A1, you can use:
=WORKDAY(A1,-3)

=WORKDAY(start_date,days,holidays)
Related formulas
Add workdays to date custom weekends
Add days exclude certain days of week
If you need to add or subtract business days (workdays) to a date so that you can calculate a date in the future or past that skips weekends (and holidays), you can use the WORKDAY function. Holidays are optional.
In the example, the formula in D6 is:
=WORKDAY(B6,C6,B9:B11)
This adds 7 days to Tuesday, Dec 22 and returns Tuesday, January 5, 2016.
By default, the WORKDAY function will exclude weekends (Saturday and Sunday). In this case, we have also supplied a list of 3 holidays that all fall in the date range being calculated, which means both the weekends and holidays will be excluded. The following table shows which dates are excluded with and without holidays provided (shaded gray). The final dates returned by WORKDAY are highlighted in yellow
| No holidays | Holidays provided |
|---|---|
| Wed, 23-Dec-2015 | Wed, 23-Dec-2015 |
| Thu, 24-Dec-2015 | Thu, 24-Dec-2015 |
| Fri, 25-Dec-2015 | Fri, 25-Dec-2015 |
| Sat, 26-Dec-2015 | Sat, 26-Dec-2015 |
| Sun, 27-Dec-2015 | Sun, 27-Dec-2015 |
| Mon, 28-Dec-2015 | Mon, 28-Dec-2015 |
| Tue, 29-Dec-2015 | Tue, 29-Dec-2015 |
| Wed, 30-Dec-2015 | Wed, 30-Dec-2015 |
| Thu, 31-Dec-2015 | Thu, 31-Dec-2015 |
| Fri, 01-Jan-2016 | Fri, 01-Jan-2016 |
| Sat, 02-Jan-2016 | Sat, 02-Jan-2016 |
| Sun, 03-Jan-2016 | Sun, 03-Jan-2016 |
| Mon, 04-Jan-2016 | Mon, 04-Jan-2016 |
| Tue, 05-Jan-2016 | Tue, 05-Jan-2016 |
| Wed, 06-Jan-2016 | Wed, 06-Jan-2016 |
To subtract business from a date (instead of adding workdays) just use a negative value for days. For example to get a date 3 workdays before a date in A1, you can use:
=WORKDAY(A1,-3)